Our scaffold continues to rise alongside construction at Waterfront Brisbane, advancing in sequence with the formwork jump system to maintain perimeter edge protection.
The latest scaffold reset is at Levels 5 and 6, using the Twix bracket system and lattice beams hung from the core wall. This arrangement allows the scaffold to progress with the formwork, with one elevation remaining open to accommodate the incoming structural steel.
Careful planning and close coordination between our design, project and site teams continue to support each stage of this complex project. Great work by our crews delivering the scaffold as construction moves upwards.